<center>
<table>
-<tr><td></td><th>CURRENT (7.5)</th><th>NEXT (7.6)</th>
+<tr><td></td><th>CURRENT (7.6)</th><th>NEXT (7.7)</th>
</tr>
<tr>
-<th>Branch:</th><td>July (2012-07-17)</td><td>February (2013-02-02)</td>
+<th>Branch:</th><td>February (2013-02-02)</td><td>September (2013-09-07)</td>
</tr>
<tr>
-<th>Pre-release:</th><td>July (2012-07-17)</td><td>[as soon as branched]</td>
+<th>Pre-release:</th><td>[as soon as branched]</td><td>[as soon as branched]</td>
</tr>
<tr>
-<th>Release:</th><td>August (2012-08-17)</td><td>February (2013-02-16)</td>
+<th>Release:</th><td>April (2013-04-26)</td><td>September (2013-09-20)</td>
</tr>
<tr>
-<th>reSpin:</th><td>November (2012-11-16)</td><td>[3 months after release]</td>
+<th>reSpin:</th><td>July (2013-07-26)</td><td>[3 months after release]</td>
</tr>
</table>
</center>
<tr> <th>Release</th><th>Estimate</th><th>Schedule</th><th>Actual</th><th>Slip (months)</th><th align=left>Comment</th></tr>
<tr>
+<td>7.6</td><td>2013-02</td><td>2013-02</td><td>2013-04-26</td>
+<td align=center>2</td><td align=left>Larger than usual number of
+regressions and critical issues detected after creating branch</td> </tr>
<td>7.5</td><td>2012-11</td><td>2012-11</td><td>2012-08-20</td>
<td align=center>2</td><td align=left></td> </tr>
<td>7.5</td><td>2012-06</td><td>2012-06</td><td>2012-08-17</td>